ARRA Stimulus Funds at Work on Minnesota's I-90
Ulland Brothers Inc. executes $15 million American Recovery and Reinvestment Act stimulus project, addressing a few extra requirements in the process
Related Content
Resources
Related Terms
When the Minnesota Department of Transportation announced the first joint transportation project to be funded by ARRA stimulus in February, Freeborn County's Hwy. 46 near Albert Lea and MnDOT's I-90, which runs parallel to the county highway in same area, would soon be moved to the front burner in a long list of state projects that would otherwise be delayed or executed in phases over several years.
MnDOT's projects included a 12-mile resurfacing of I-90 from the west limits of Alden to Hwy. 13 near Albert Lea, and Freeborn County's project consisted of a concrete overlay of Hwy. 46 from Arena Road in Albert Lea to Alden.
Because the two projects were located so close to one another, county and state officials decided to submit them as a joint project to take advantage of the economies of scale and to minimize disruption to the traveling public.
Total estimate for the joint project was $17.6 million, with Ulland Brothers of Albert Lea winning the primary contractor bid of just under $16 million. Submitting the two projects as a joint project did help the county and state road agencies enhance their abilities to secure stimulus funding for the two, considering the numerous projects that applied for Minnesota's portion of the ARRA $27.5 billion road and bridge fund.
The joint project is one of nearly 100 Minnesota road and bridge projects that will be funded with $502 million in federal economic stimulus dollars. If the joint project had not been selected to receive stimulus funding, the I-90 portion would not have been completed until 2011. The funding also allowed Freeborn County to advance several other projects to this year's construction season.
I-90 project details
The I-90 portion of the joint project was constructed in two phases. During the first phase of the project, the two eastbound lanes of the interstate were resurfaced with a concrete overlay.
Ulland crews placed 12,000 tons of a permeable asphalt stabilized stress relief course (PASSRC) over the existing concrete roadway before a new concrete surface course was placed.
The PASSRC mix design not only provides drainage underneath the concrete overlay, but it also serves as a bond breaker between the old roadway and the new overlay.
During the second phase of the project, Ulland paving crews placed three 1.5-inch lifts of Superpave (SPWEB440E) hot mix asphalt over the existing concrete westbound lanes.
On the westbound lanes, the original concrete under bridge structures had to be milled out to accommodate the new thickness of the asphalt overlay. It was also necessary to remove any unstable chunks of concrete and replace it with bituminous mix.
The construction specifications also called for correcting the slope on the travel lanes from 1.5% to 2% to improve drainage. This was done with the first leveling course where in some areas, especially along the curves, five to six inches were required along the inside shoulder to obtain the corrected slope specifications.
On the 10-foot-wide outside shoulder, Ulland performed a full-depth reclamation of the asphalt and base aggregate before placing a 3.5-inch Superpave (SPWEB230B) overlay.
Ulland performed all the concrete and blacktop removals required for the project, along with subcutting and grading of all adjacent ditches. The contractor also placed select granular Class 5 base, Class 5 shoulder and blacktop in subcuts for the project.
Ulland has been an industry leader in highway and airport building and repair for over 70 years. The project was supplied with HMA produced at the company's Glenville asphalt plant, a high-production Gencor facility equipped with four silos and a load-out system that allows for multiple mix design production and fast loading for Ulland crews and outside customers.
Extra details
For Ulland's Jeff Carlson, general manager of the Albert Lea division, and Andy Erichson, project manager, the joint I-90/Hwy. 46 project was typical of most asphalt projects with the exception of a few additional requirements outlined by the stimulus program.
- « Previous Page
- 1
- 2
- Next Page »

