Constructing a better longitudinal joint

How do you make a pavement joint last longer?


For as long as there have been paved roads, there have been questions about the longitudinal joint between lanes. How do you make the joint last longer? How do you prevent raveling, cracking and erosion? How do you prevent water infiltration? What are the critical factors? It?s always been assumed that what was most critical for good road performance was density.

Over the years great attention was given to analyzing the effect of density, both on the main part of the mat and at the joint region. Mix designs have concentrated on maximizing the achievable density.

Screed designs aimed at increasing the initial density that could be achieved as the asphalt left the paving machine. The hope was if density could be achieved in spreading the asphalt initially, then it would alleviate the necessity of increased rolling.

With regard to the rolling of asphalt, roller weight was maximized. Roller vibration was introduced in hopes of moving aggregate and nesting it in a more close packed geometry, hence increasing density. Vibration was also added to the paving machine in an attempt to increase initial density.

With all this attention given to density, the performance of the longitudinal joint did not appreciably improve. Looking at the actual joint geometry seemed a logical step.

Up to this time, the joint between lanes was essentially a vertical butt joint. When rolling the initial lane, the downward force of the roller translated into movement of the material horizontally. Even though tack material would be sprayed on the subsurface prior to the application, this would only tend to hold the bottom of the material.

Since movement was allowed, this translated into decreased density at the edge of the mat as compared to the center. When laying the adjacent lane, the first edge acted as a form so the new material had nowhere to go under the pressure of the roller.

Thus the density of the edge of the closing lane would tend to be greater. However, the total bulk density of the material across the joint was still substantially less than the adjacent area. Also, the performance of the joint relative to cracking, raveling and erosion remained the same.

Improving joint density

Given the above, work was done on improving the density of vertical joints by producing a device which increased the amount of asphalt passing under the screed in a region 4 to 8 inches from the end gate. The additional volume of asphalt would result in increased density in that region. This initial increase was thought to be carried over the rolling process.

Testing confirmed that the joint region exhibited improved density and improved performance. The tests were performed on airport paving of taxiways and runways with thick mats. When tested on highways with thinner lifts, the results were not as dramatic and in some cases no improvement was noted. The debate over the effectiveness of the joint maker device continues and testing to confirm its claims is ongoing.

Two joint configurations

Another approach to the problem of longitudinal joint life and performance resulted in two significant joint configurations. The first was the Jersey Joint configuration. This was basically a taper of approximately a ratio of 1:12 lift to run.

Several benefits resulted. First, the ramp allowed for traffic transition from the unpaved lane to the paved one and back. This resulted in fewer transverse joints, since paving could continue in one direction without having to close the adjacent lane each day. Joint performance once closed appeared to improve. This was thought to be density related.

One major disadvantage was that the ramped edge tapered to less than a stone height. This caused an unraveling effect of the seam edge, resulting in failure of the joint. Subsequently, a new geometry called a Michigan Joint was developed.

This configuration had the same ramp effect, which allowed for traffic transition, but also featured a vertical notch of a predetermined height adjacent to the ramp. This notch allowed for seaming the two adjacent lanes without unraveling.

This content continues onto the next page...