Repairs in Review

With numerous concrete panels experiencing faulting over the years due to the loss of load transfer, it was time for a five-mile stretch of U.S. Highway 195 to be repaired. A major artery connecting Spokane, Wash., to Lewiston, Idaho, the concrete pavement dated back to the mid-1960s. Acme Concrete Paving, Inc., located in Spokane, Wash., took on the project using dowel bar retrofit as the repair method.

Jim Allen, project manager, says DBR was chosen because it is a cost-effective repair option that doesn’t require removing and replacing the whole road. “Over time the concrete faults at the joints, and then the roads get rough,” Allen says. “This stabilizes it from happening again.”

To complete the repairs, Acme Concrete used two concrete cutting and breaking slot saws. The saws cut three slots at a time with a group of three slots in each wheel path.

First, the crew would cut the slots and then jackhammer out the concrete in between the saw cuts. After that, the crews would prep the slots by sand blasting them and sealing the transfer joints so the mix wouldn’t run down the joint. Next, they placed the dowel bars in the slots.

During the day, traffic was reduced in some areas while the crew completed the repairs. Crews completed prep work on 1,000-foot stretches of roadway, spending 10 to 15 minutes at each joint.

Finally, crews poured Rapid Set DOT Repair Mix from CTS Cement into the slots and then put a curing compound on the surface. Using mobile mixers, the crew had a continuous mix process mixing just enough Rapid Set mix to fill the six slots and move ahead.

After the mix set, the crews would come back and re-cut the joints. When the project was completed, Acme Concrete had installed 8,500 DBRs between the existing concrete panels.

The biggest challenge Allen and his crew faced was the weather. “We started in spring and the weather was really wet,” he says. “You can’t do dowel bar retrofits when it rains because you can’t cover the holes to prevent the water from getting in.”

 

Turning the look of old concrete into new

After years of heavy foot traffic, the sidewalks around the San Francisco International Airport departure area were damaged and spalled. DSM Structural Concrete Services of Grass Valley, Calif., was hired to repair the sidewalks. Donnie Militano, owner, saw repairing the existing concrete as the best option for the project.

To complete the repairs, DSM Concrete went with ARDEX CD Fine concrete dressing, a portland cement-based repair product with polymers. ARDEX CD Fine produces a new wear layer and fills in small surface defects such as gouges and cracks. By using ARDEX CD Fine, DSM Concrete was able to resurface and restore without having to remove and replace the concrete surfaces, ultimately making the repaired areas look like new. San Francisco airport chose a black repair mix because the original curbsides were black when they were poured, Militano says.

The project began with the DSM Concrete crew blasting the area with 4,000 psi hot water to both clean the area and open up the pours of the concrete. Then, the crew applied two coats of ARDEX CD Fine. Crew members did this by first troweling down a scratch coat. Next, the crew trowel applied the top coat and used a flexible-blade trowel to wipe out all of the lines on the top coat.

About a half an hour after the repair product was applied, the surface was dry and the crew was able to apply a water-based, acrylic urethane concrete sealer.

In order to work with the high foot-traffic area, DSM Concrete completed the project 200 lineal feet at a time. “We would barricade a section off,” Militano says. “Then we would apply the sealer, and then we would open it up to the public.” The sections were open to foot traffic within three to four hours of completing the repairs.

DSM Concrete completed about 1,000 square feet a day, finishing the project in four months, Militano says.

The completion of the sidewalk repairs was so successful that the project was expanded to include the island areas and curbs. By the end of the project, DSM Concrete resurfaced 90,000 square feet at the San Francisco airport.

 

Speed is critical on repairs at the Nassau Expressway

The Nassau Expressway serves as a major artery leading to JFK International Airport outside of New York, N.Y. Approximately 40 years old, the roadway has seen increased traffic demands since its inception and recently underwent extensive repairs to several miles of its concrete pavement.

The New York DOT contracted Tully Construction, Flushing, N.Y., to perform both partial-depth concrete patching and full-depth repairs along three miles of the roadway. Because the Nassau Expressway is such a heavily used roadway, the New York DOT required repairs be done at night, between 9 p.m. and 6 a.m., with only minimal road closures. Tully devised a closure strategy and safety plan that allowed traffic to flow adjacent to the lanes being repaired.

Tully Construction performed the partial-depth patching with ProSpec Premium Patch 200. Mixed with 38-inch stone, the fast-setting, rapid strength gain repair product can be opened up to traffic in one to two hours. The Tully crews mixed the material on demand with a mobile mixer, which kept aggregate, water and patch materials separate until the mix was needed. The working time of the field mixed concrete is approximately 20 minutes.

DOT inspectors identified and marked the areas that required patching. Tully saw cut a rectangular perimeter around each area and removed the unsound concrete using lightweight pneumatic hammers. The Tully crews placed the mix directly from the mobile mix machine onto the roadway.

ProSpec Premium Patch 200 requires minimal finishing and texturing work. On the Nassau Expressway project, the material set in about 30 minutes, and crews were able to open up the repair area to traffic after about an hour. Tully used 2,500-pound super sacks of the patching material, purchased through construction materials supplier Axela Services, LLC. In all, about 7,000 square feet of pavement was repaired.

Other sections of the Nassau Expressway were in need of repairs beyond partial-depth patching. Those areas received full-depth repair with Super-Slab precast concrete panels by The Fort Miller Co., Inc. The Super-Slab is a precast slab-on-grade system for highway, exit ramp, airport pavement and other roadway replacement. The slabs are crane set, and adjacent panels are connected with load transfer dowels.

“The advantage of this system is speed,” says Joe Rizzo, Northeast district sales manager with ProSpec. “They can perform full-width, full-depth repairs with nighttime closures instead of months behind barriers and the time it takes to pave. And they can open the road to traffic the next day.”

The placement of the Super-Slab precast concrete panels required the Tully crews to take down the existing road to the subbase. Crushed stone aggregate was placed and graded and the panels lowered on top. ProSpec’s Slab Dowel Grout was used to fill in around the load transfer dowel slots and also to fill in any voids between panels and existing pavement.

Throughout the Nassau Expressway project, Tully crews placed 1,500 Super-Slab panels. Fourteen trucks of Slab Dowel Grout were placed using a Machine Technologies automatic water feed mixing pump.

Repair of Route 66

U.S. Route 66 — the “Main Street of America,” as it is known to many — dates to 1926 and is a quintessential American icon. But, even landmarks such as the “Mother Road” need to be repaired every so often to keep them up and running for another generation.

So, city officials in Winslow — the city made famous by The Eagles’ 1972 hit song “Take It Easy” — selected Phoenix-based dbA Construction to repair this famed federal highway. The 2009 project comprised of a full-depth and partial-depth repair of a 12-block section in downtown Winslow. In total, dbA Construction used 8,610 70-pound bags of QUIKRETE FastSet Concrete Mix for the project.

“QUIKRETE FastSet Concrete Mix had the right setup time with the traffic control constraints and the phasing of the project,” said Jay Cano, project manager for dbA Construction. The product achieves 3,000 psi in three hours and 7,000 psi in 28 days, and provides 20 to 30 minutes working time for mixing, placing and finishing operations. The fast setting, high early strength concrete mix is designed to build or repair sidewalks, driveways, highways, bridge decks, parking lots and floors. It has less shrinkage than ordinary portland cement concrete, and the mix is available with an integral corrosion inhibitor.

Crews were able to keep lane closures to a minimum, ensuring traffic flowed through Winslow while the roadwork was completed. Of course, the location also added to the overall uniqueness of the project. “Working on Route 66 and getting to see all the tourists coming to stand on the corner of Winslow certainly made this project unique,” Cano said.

Additional reporting by Rebecca Wasieleski and Kimberley Schmitt

Loading