Runway Project Makes for Challenging Paving Project

General Asphalt builds team to tackle short Miami International Airport runway/taxiway paving window.


In the end, additional work and unforeseen events prompted MDAD to extend the deadline for completing Phases 3 and 4 by 11 days. "While we extended this deadline, we are still on target to meet the overall 454-day contract deadline," says Beltre.

On Tuesday, June 8 at 6:45 p.m., Runway 8R 26L was turned over to MDAD and aircraft, once again, were taking off and landing on the runway. This time with a fresh, smooth asphalt surface designed to give the Aviation Department two decades of trouble-free service.