MN Wind Farm Construction Employs First Manitowoc MLC650 Crane in US

Bigge Crane and Rigging was the first company to put the Manitowoc MLC650 to use erecting 18 wind turbine towers in Minnesota

The MLC650 erected wind turbine blades that weighed 12.5 tons each at heights up to 295 ft.
The MLC650 erected wind turbine blades that weighed 12.5 tons each at heights up to 295 ft.

The challenge:

Erecting a large, Minnesota wind farm using the first Manitowoc MLC650 crane in the country

The players:

Bigge Crane and Rigging
Renewable Energy Systems America

The process: 

Bigge Crane and Rigging was the first company to put the Manitowoc MLC650 to use, employing the innovative crane to erect a large wind farm in the U.S. state of Minnesota. The MLC650 features the Variable Position Counterweight (VPC), a unique floating counterweight design.

The San Leandro, CA-based company rented the MLC650 to Broomfield, CO-based Renewable Energy Systems America (RES), which used the crane to erect wind turbines at the Pleasant Valley Wind Farm near Austin, MN. The company used the crane to erect 18 towers on a 200 MW-generating project that was scheduled for completion in late 2015.

Weston Settlemier, president and CEO of Bigge, said the MLC650 offered several advantages over other large crawler cranes for the wind farm project.

“Moving forward, we expect the wind turbine market to demand the MLC650 over the current offering of crawler cranes because the VPC saves time and money” he said. “The crane’s technology allows for reduced erection time, increases walking speeds and reduces transportation costs. In addition, the VPC balanced technology reduces the point loading of crawlers and reduces ground preparation required by the wind turbine erection contractor.”

On the site, the MLC650 was configured with 341 feet of main boom, 24.9 feet of extended upper boom and only 326 tons of counterweight. The crane lifted prefabricated wind tower sections and turbines (nacelles) in loads weighing up to 118 tons. It also erected the blades that weigh 12.5 tons each at heights up to 295 feet. The VPC system dynamically positions the MLC650’s counterweight to suit each lift. The counterweight moves along the rotating bed and is automatically positioned based on changes in operating radius. 

Beyond the crane’s setup, Bigge said there were even more features of the crane that offer benefits over competitive crawler cranes typically used on wind farms. For one, the MLC650 doesn’t have a fixed mast; it has a smaller, live mast, making it easier to move around the jobsite. Power lines are often found on wind farm sites that require cranes with fixed masts to be disassembled so they can move underneath them before they’re reassembled again on the other side. The MLC650’s mast doesn’t require as much disassembly to lower its height, meaning less down time and less prep time.

John Krane, leasing manager with Bigge, said the MLC650 offered several advantages over other large crawler cranes for the wind farm project.

“One of the MLC650’s biggest selling points for me is its larger wire rope and greater line pull,” Krane explained. “It can work with six parts of line, rather than eight parts. These features make the crane’s hoisting much faster than other cranes, which will enable us to complete this job in a shorter amount of time. Also, it doesn’t need an assist crane to raise its boom, again saving us time and money.”

As the MLC650 was new to Bigge, Manitowoc Crane Care sent representatives to the Minnesota jobsite to ensure that the crane’s erection and operation went smoothly.  

“I’ve been very impressed with the MLC650,” Krane said. “The new VPC technology is great, and the assembly and initial operations went very smoothly. It was in great shape and ready to go, right out of the box.”