Obama Selects 14 Infrastructure Projects for Expedited Approvals

Lessons learned expected to guide federal regulatory reform


Located in Washington, DC, City Market at “O” Street is a mixed-use property consisting of 400 market-rate residential units, 16,000 square feet of retail space and a 57,000 square foot supermarket with financing under the Federal Housing Administration (FHA) Section 220 insured mortgage program. In conjunction with this project and others, FHA has embarked on an effort to streamline the approval process for loans, including review of related federal permits and is working with the Advisory Council on Historic Preservation to expedite the National Historic Trust approval, subject to Section 106 of the National Historic Preservation Act.

Department of Commerce

Arroyo Sequit Watershed and Qwuloolt Estuary Coastal Habitat Restoration Project, California

This habitat restoration project is composed of two activities. The first activity is the Arroyo Sequit Creek Steelhead Barrier Removal in California, which will involve construction activities to remove existing physical barriers, including two dry weather crossings and one check dam, along the Arroyo Sequit watershed in northern Los Angeles County, CA. The second activity is the Qwuloolt Estuary Restoration in Washington State and will involve restoration construction activities to restore 350 acres of currently isolated floodplain. The National Oceanic and Atmospheric Administration will work with the Army Corps of Engineers to expedite construction permits by up to one year, with the goal of beginning construction as early as 2012.

West Coast Coastal Habitat Restoration Project, California and Washington

This project is composed of four habitat restoration activities including Sears Point Tidal Restoration in California; Napa River Salt Marsh Restoration in California; Riverside Ranch Restoration in California; and the Salt Creek Estuary Reconnection in Washington State. The scope of these project activities will involve construction elements that will contribute to habitat restoration in these regions. This project will be expedited by up to one year by the facilitation of interagency resource coordination between the Army Corps of Engineers and the National Oceanic and Atmospheric Administration.

Department of Agriculture

Cleghorn Ridge Wind Project, California

This wind generation project by Cleghorn Ridge Wind LLC would consist of up to 52 wind turbine generators aligned in a general east-west direction along the ridgeline at Cleghorn Ridge, in the San Bernardino National Forest. USDA Forest Service, U.S. Air Force, and Federal Aviation Administration will cooperate to complete the review of this project by federal agencies in as little as 18 months, rather than the three years originally estimated.

Deerfield Wind Power Project, Vermont

This wind generation facility by Deerfield Wind LLC in the towns of Searsburg and Readsboro in the Green Mountain National Forest in Vermont would consist of 15 two-megawatt turbines. USDA Forest Service is working to expedite a Final Environmental Impact Statement before December 2011.

Dakota Prairie and Little Missouri National Grasslands, North Dakota and South Dakota

USDA Forest Service is working with an expedited process for reviewing oil and gas applications for wells and ancillary facilities such as pipelines and power lines in the Dakota Prairie and Little Missouri National Grasslands. There are approximately 80 applications currently in file. The expedited process involves early coordination with the U.S. Department of Interior Bureau of Land Management and use of the 390 Categorical Exclusion provided under the 2005 Energy Policy Act.

In addition to unveiling the projects selected for expedited review today, the Administration will also instruct agencies throughout the executive branch to gather comprehensive information regarding their reviews of infrastructure projects, and the best practices they have developed. The Administrationwill use that information to develop recommendations to further improve the efficiency, effectiveness, transparency and accountability of federal permitting and environmental review, without compromising our responsibility to protect safety, public health, and the environment, through measures such as adopting sector-specific guidelines for timely reviews of permitting applications; encouraging early engagement with stakeholders; coordinating federal reviews with those of state, local and tribal regulatory agencies; and instituting greater oversight of the overall process.