Dowel Bar Retrofit Process Celebrates 30 Years

Dowel bar retrofit repairs have been proven to last between 15 and 20 years, according to state monitored projects

The proper DBR approach is to saw cut and jackhammer out the slots for the dowels; following dowel placement, the slots are then typically backfilled with a non-shrink concrete grout and the pavement is diamond-ground to restore smoothness.
The proper DBR approach is to saw cut and jackhammer out the slots for the dowels; following dowel placement, the slots are then typically backfilled with a non-shrink concrete grout and the pavement is diamond-ground to restore smoothness.
International Grooving And Grinding Association Logo 60103d7eabd6e[1]

 The method of retrofitting load transfer devices across transverse joints and cracks in concrete pavement has been used successfully on thousands of (lane) miles in the United States with more than 6.5 million dowel bars installed during the past 30 years.

The first installation of dowel bar retrofitting (DBR) was completed in 1981 on I-75 in Georgia as part of a research study to determine how to reestablish load transfer in existing PCC pavements. The Georgia Department of Transportation became interested in improving the load transfer capabilities of existing PCC pavements after observing the re-faulting of pavements following diamond grinding and concrete pavement restoration (CPR). It was felt that the effectiveness of CPR could be extended if load transfer could be added at the joints. The goal was to develop construction procedures for adding load transfer to existing pavements and to evaluate the effectiveness of the methods.

Various load transfer devices were placed by maintenance forces in a total of 461 joints on I-75 between Atlanta and Macon in 1981, and some additional installations were done in 1982. Almost three miles were repaired through the extensive effort. The DBR concept was developed during this research study by cutting the slots, placing smooth steel dowels within and backfilling using various slot filling materials. The follow-up evaluations concluded that dowel bars were the best solution to establishing load transfer to existing joints.

"We are excited to see that after 30 years, DBR is being used by even more municipalities as an environmentally friendly, economic long term repair," said John Roberts, executive director of The International Grooving and Grinding Association. "This technique has spread throughout the U.S. and Canada as a viable means of preserving concrete roadways."

DBR is a CPR technique that restores load transfer capability of existing jointed concrete pavement by the placement of dowel bars across joints and cracks that exhibit poor load transfer. The retrofit dowel bars ensure that the traffic load is shared between adjacent panels, preventing differential vertical move­ment of the slabs at the joints and cracks, thereby eliminating the formation of faults or step-offs. These faults are the cause of the rough ride and wheel slap that is sensed when traveling on a con­crete roadway that has lost its ability to transfer load from one panel to the next.

Since its inception, numerous states have successfully used DBR to address faulting in older jointed plain concrete pavements. The proper approach is to saw cut and jackhammer out the slots for the dowels. Following dowel placement, the slots are then typically backfilled with a non-shrink concrete grout and the pavement is diamond-ground to restore smoothness.

"The evidence of DBR's effectiveness is there, revealed through time and experience," said Roberts. "DBR will continue to grow as municipalities look for more cost-effective solutions to meet their growing need for infrastructure repairs."

DBR repairs have proven that they will last from 15 to 20 years and likely even longer as documented by states that monitor their DBR projects. The method is environmentally friendly as it repairs the existing pavement with very little new natural materials required. Also, keeping the pavement's light concrete surface reduces the heat island effect as these pavements reflect more light than dark asphalt surfaces, which in turn reduces roadside lighting requirements.

Projects can be completed during off-peak hours with short single lane closures allowing the roadway owner to repair only the lanes that show distress. 

Following the installation of the DBRs, the surface of a roadway is then diamond ground to restore and improve smoothness. This process also enhances surface friction and safety while significantly reducing tire/pavement noise. Diamond ground roadways typically have a smoothness level equal to and often better than original construction.

Latest