.jpg)



Three months into a scheduled three-year project may seem a little early to gauge the progress Ajax Paving Industries Inc. of Florida is making on the I-75 project, but Vic OHara, Ajax Ft. Meyers area manager, and Mark Minich, Ajax vice president and member of the joint-venture projects executive team, agree that the work already completed is pretty good indication that progress is definitely being made.
The first phase of this project required us to strengthen the outside shoulder to accommodate the traffic load while were working on the (two existing) travel lanes, OHara notes. We removed the two-inch shoulder pavement and three inches of base below it, and then placed a full five inches of asphalt to give the structural strength needed to handle traffic for the duration of the project.
Weve already (mid-January) rebuilt 18 miles of shoulder and weve already milled and filled 18 miles of the existing travel lanes (from the south end of the project in Naples going north), he continues. Were milling 2 1/4 inches off and placing an 1 1/2 inch lift of new mix on the existing travel lanes.
Milling and paving operations are only allowed between 8 pm and 5 am, with the Ajax paving crew placing 1,800 to 2,300 tons of polymer-modified mix each night.
Whatever we mill has to be replaced before the lane is opened up to traffic in the morning, OHara notes.