ForConstructionPros.com

Article

  

Jobsite Solutions

Updated: July 8th, 2008 05:26 PM GMT-05:00

Crushing Cuts Highway Project Costs

Jobsite Solutions

Terex Pegson 26x44 jaw
To crush 185,000 tons of additional rock encountered during the Highway 49 Bypass project, Eland Construction utilized Terex Pegson 26x44 jaw and 1300 and 1000 model cone crushers with a Powerscreen Chieftain 1800 and two Powerscreen radial stackers.
Crushed material
The hilly terrain along the bypass was filled with dense, igneous rock. To save on hauling and material costs, road builder Stimpel-Wiebelhaus worked with Eland Construction to crush the material on site.

By Equipment Today Staff

The new four-lane Highway 49 Bypass in Northern California begins a little south of historic Sutter Creek and ends just north of Amador City. The bypass is 4 miles long and involved the building of two major bridges.

Primary contractor on the project was Viking-Stimpel, a joint venture between road builder Stimpel-Wiebelhaus Associates, Redding, CA, and bridge builder Viking Construction, Rancho Cordova, CA.

The project site presented unexpected challenges for Stimpel-Wiebelhaus. Not only was it very hilly, it was full of greenstone, a dense, igneous rock. Much more of this rock was encountered during excavation than expected.

"We had bid the job very aggressively," says Bill Wiebelhaus, operations manager. "I believe we were about $2 million below the closest bidder. The job required about 700,000 tons of off-haul. We knew we could make quality road base from the rock excavation. But we were limited on stockpile room in the highway right-of-way - such that we could only make about half of the 120,000 tons required."

What to do with all that rock?
The question became what to do with the excess shot-rock excavation. Potential waste sites on properties adjacent to the job were in use for agricultural purposes.

1 2 3 4 5 next
E-mail This StoryE-mail Article Print This StoryPrinter Friendly