Slide Rail Overcomes Obstacles

Jobsite Solutions

The excavation site for the 47-ft.-long fuel tank had very limited access and various obstacles, including a loading bay dock along one side and newly installed electrical banks on the other.
An unobstructed opening of more than 55 ft. was made possible by utilizing Efficiency Production’s Parallel Beam cross-trench support design.
Jim Wright (left), United Rentals Trench Safety, discusses installation of the slide rail system with Stan Burnside (right), Tonn & Blank Construction Co.

Related Articles

Read More Jobsite Solutions

Moving Earth and Iron

Becky Schultz
By Becky Schultz
Editor

St. Francis Hospital in Indianapolis, IN, is in the midst of a $265 million expansion. Upon its completion by mid-year 2010, the hospital campus will have a new emergency room, six-story inpatient tower, surgical suites and additional space for support services.

As part of the expansion, Tonn and Blank (T & B) Construction Co., Michigan City, IN, the construction subsidiary of the Sisters of St. Francis Health Services, Inc., is installing a 30,000-gal. fiberglass fuel tank measuring 47 ft. long and 12 ft. in diameter. The tank will be used to fuel the hospital’s backup generators.

The excavation site was located about 6 ft. from the hospital. Nearby obstacles included a loading bay dock directly along one side that had to stay open throughout the excavating and installation process, and newly installed electrical banks just a few feet on the other side. As a result, excavators and other equipment could only access the site from two sides.

Slide rail proves the only option

Clearly, shoring the excavation to T & B’s strict safety standards was going to be a challenge. So Stan Burnside, T & B’s foreman, contacted Jim Wright, branch manager at United Rentals Trench Safety in Indianapolis.

“After looking at the specs of the project, I could see that our options were very limited,” admits Wright. Vibration restrictions at the hospital prevented the use of vibratory hammer-installed sheeting and bracing. “Also, installing a beam and plate or lagging system was off the table due to the two week schedule given to complete the project.”