ForConstructionPros.com

Article

  

Features

Bookmark PageBookmark Page Most Read Stories TodayMost Read Most Emailed Stories TodayMost Emailed + -
Updated: July 8th, 2008 05:26 PM EDT

Pieces of Silver

Commerical paving

Silver Spring paving
"Work on the Silver Spring job was pretty much an on-call situation," says Frank Smith, project manager. "As areas were ready we were called in to do our portion of the construction."
Pennsy Supply Construction Group
"It’s always a challenge to work around other construction crews," says Barry Harbonic, vice president, Pennsy Supply Construction Group. "There has to be some give and take with each subcontractor, and that’s where the meetings really came in handy"
Pennsy Testing Depth
Paving on the Silver Spring Square Retail Center ranged from as little as 150 to 200 tons a day to as much as 2,000 tons a day.
Pennsy rolling
Internal Pennsy Supply planning meetings included the contractor's master mechanic, who needed to know the contractor's equipment needs for the upcoming weeks.

Allan Heydorn
By Allan Heydorn
Editor

Every paving job has its own challenges, and when Pennsy Supply took on the job of grading and paving the Silver Spring Square Retail Center, they knew scheduling was going to their biggest obstacle. Not only was Silver Spring Square the biggest commercial paving project Mechanicsburg, PA, has seen in years, but the contractor who did the job was going to have to be at the beckon call of the general contractor, paving in whatever bits and pieces were available.

But that didn't phase Pennsy Supply a bit. And now, as the job nears completion more than 18 months after it was begun, Pennsy has met the challenge through experience, extensive planning, and effective utilization of equipment and crews.

"It was tough because we couldn't go in and pave the way we would normally pave," says Frank Smith, project manager. "Because of the nature of the project, with some areas opening before others and because we were working around so many other contractors, we had to pave as areas became available to us. So it was a challenge to maintain the quality throughout the project, but the crews did a great job and we passed all the quality control tests they did."

An Oldcastle company, Pennsy Supply covers central Pennsylvania with six asphalt plants and seven quarries, producing between 900,000 and 1 million tons of hot mix asphalt a year. Barry Harbonic, vice president of Pennsy Supply Construction Group, says Pennsy places 400,000 tons of mix on its own jobs, and sells 60% of the mix it produces to other contractors. He says 40% of Pennsy Supply's paving is roadwork for PennDot, with the bulk of that being large-scale milling and overlay jobs. Most of the paving work (60%) is on commercial projects, so the Silver Spring Square Retail Center fit nicely into its operation. Harbonic says Pennsy employs 500 people throughout its entire operation, 60 of whom work in the construction division, which operates five paving crews, three grading crews, a prep crew, and a production-milling crew.

"With five paving crews you can get an awful lot of work done if you have the material and have the schedule," Harbonic says. "You can lay a lot of material in a day."

1 2 3 4 5 6 next
[Get Copyright Permissions] Click here for copyright permissions!
Copyright 2008 Cygnus Business Media