ForConstructionPros.com

Article

  

Paving Innovations

Bookmark PageBookmark Page Most Read Stories TodayMost Read Most Emailed Stories TodayMost Emailed + -
Updated: January 22nd, 2009 12:44 PM EDT

Oregon Mainline Paving, LLC achieves ride smoothness bonus on new U.S. 97 realignment project in Redmond, OR

Asphalt Paving

Oregon Mainline Paving
Oregon Mainline Paving, LLC achieves ride smoothness bonus on new U.S. 97 realignment project in Redmond, OR
The bypass, which runs between the Central Oregon Irrigation District's Pilot Butte Canal and the BNSF Railroad on the east side of Redmond, handles a daily traffic count of 35,000 vehicles, 12 to 15 percent being trucks.
The Bulletin, Bend, OR
With a new 10-inch aggregate base and 10-foot concrete median barrier in place, the contractor's paving crew took over in placing approximately 110,000 tons of ODOT Level 3 12.5mm dense-graded Superpave hot mix asphalt to construct an 11-inch-thick perpetual pavement structure.
For Oregon Mainline Paving, meeting the smoothness and mix quality requirements of the project represented approximately $250,000 in additional bonus pay.

Greg Udelhofen
By Greg Udelhofen
Editor

The pavement was placed in four lifts, with the three 3-inch base/binder courses consisting of a PG 64-28 AC, ½-in. aggregate dense mix with lime additive to prevent stripping. The top 2-inch wearing course was produced with a PG 70-28 AC binder, ½-inch aggregate and lime additive.

"The contract called for a rich mix design (6.5 percent) and an anti-stripping agent (lime)," Seehawer says. "We were also allowed to use up to 30 percent RAP (reclaimed asphalt pavement) in the mixes we produced and placed; but since we were constructing a new road, we didn't have a RAP resource and had to go with all virgin materials."

Echelon paving
Since the U.S. 97 project was a new road, the contractor's crews had the luxury of working without the traffic challenges normally associated with a typical mill and fill project.

"We had as many as four different pavers (Blaw-Knox) on the project at any given time, allowing us to pave in echelon," Seehawer says. "Paving in echelon not only allowed us to increase production, but also allowed us to achieve better longitudinal joints, especially between the two mainline travel lanes and do so using only three or four (IR) double-drum vibratory rollers."

Without traffic concerns, paving crews were also able to extend screeds to hot-lap turning lanes and other expanded areas, which eliminated longitudinal joints in the process. Along with the two 12-foot-wide travel lanes in each direction, the paving crews also constructed a 10-foot-wide outside shoulder and a 7-foot-wide inside shoulder along the concrete barrier.

[Get Copyright Permissions] Click here for copyright permissions!
Copyright 2009 Cygnus Business Media