ForConstructionPros.com

Article

  

Plant Matters

Bookmark PageBookmark Page Most Read Stories TodayMost Read Most Emailed Stories TodayMost Emailed + -
Updated: May 7th, 2009 03:32 PM GMT-05:00

C.W. Roberts Brings Warm Mix to Fort Myers

CW1
In addition to making a variety of mixes including Superpave, C. W. Roberts’ new plant is capable of making warm mix asphalt, since the Florida DOT is encouraging contractors to make a change to warm mix where possible.
CW2
Even with the Florida economy in recession, C.W. Roberts purchased a new E3-400 counterflow plant fo fill internal demand and to develop an FOB market.
CW3
The first warm mix asphalt produced by the plant was run at 265 degrees F and burner positioning dropped from 55 to 40%. Initial estimates point to a savings of 0.8 gal per ton of fuel oil and 0.2 to 0.3% lower AC content in the warm mix.
CW4
After purchasing Cougar Contracting, C.W. Roberts saw an opportunity to expand the contractor's project base to include highway and interstate paving.

By Asphalt Contractor Staff

"The crews loved working with the warm mix," adds Thaw.

With the successful test and the Florida DOT encouraging use of warm mix, C. W. Roberts plans to use warm mix asphalt wherever possible.

[Get Copyright Permissions] Click here for copyright permissions!
Copyright 2009 Cygnus Business Media