Updated: July 8th, 2008 05:26 PM EDT
Doing what they do best
Contractor makes switch to asphalt sealer.
One million-sq.-ft. job was a big step up for the contractor and presented a variety of challenges even before the issue of material came up.
Originally a driveway sealcoating contractor, Maul Asphalt & Sealcoating decided that if they were going to make "serious money" in the pavement maintenance industry they would have to expand into the commercial market. Today 95% of Maul Asphalt's work is for commercial customers.
Maul Asphalt & Sealcoating usually prepares pavement for sealcoating using walk-behind power blowers, but for the 1-million-sq.-ft. AMC Cantera job, the biggest job theyd ever tackled, the company spent $500 to have the parking lot swept by a contract sweeper.
On the first day an 8-person crew began repairing 55,000 linear feet of cracks. Two workers cut in much of the parking lot to speed spraying, then three 2-person teams began spraying the first of two coats of sealer. Eventually Maul Asphalt painted more than 100,000 linear feet of striping and brought in a subcontractor to install thermoplastic arrows and stop bars.

By Allan Heydorn
Editor
"We have our trimmers trim ahead for next day if we can be assured people aren't going to get into the trim work overnight," Maul says.
Eventually Maul Asphalt coated the lot twice, Rowe striped more than 100,000 linear feet, and they hired a subcontractor to install thermoplastic stop bars and turn arrows at the parking lot entrance.
"The main entrance driveway was the most difficult part of the job because it's the only entrance in and out with a traffic control device so it couldn't be closed, plus it required thermoplastic markings," Maul said. So they showed up at 1 a.m. to get the entrance done, increasing some additives to speed sealer drying so the thermoplastic sub could get on and off quickly.
"We were on and off in four days, and we're very proud of that and the client appreciated that too," Maul says. "As a result of this we got another AMC Quarry cinema job and they wanted us to sealcoat it in the fourth week of October and we wouldn't do it because of the weather."
Maul suggested cracksealing the lot in the fall and then waiting until this spring to sealcoat.
Printer Friendly