Terex Vario-Superlift Helps Contractor Navigate Difficult Wastewater Plant Lifts

With its 440-ton capacity, the Terex crane offered power to lift the heavy loads, and its Vario-Superlift structure feature proved to be the X-factor Sterett needed to successfully maneuver about the site at full load

For lifting the massive lids, the CC 2400-1 was configured with 137 ft. of main boom. Crew members added 264,500 lb. of counterweight to the superstructure and additional 44,000 lb. of central ballast. The crane was equipped with the full 98.4 ft. of Superlift mast, and the tray was loaded with 352,700 lb. of counterweight.
For lifting the massive lids, the CC 2400-1 was configured with 137 ft. of main boom. Crew members added 264,500 lb. of counterweight to the superstructure and additional 44,000 lb. of central ballast. The crane was equipped with the full 98.4 ft. of Superlift mast, and the tray was loaded with 352,700 lb. of counterweight.

The challenge:

Find a crane small enough to fit into a tight, congested jobsite but still offer the capacity to lift heavy loads in excess of 250,000 lb. 

The players:

Sterett Crane & Rigging
Bowen Engineering

The process:

Periodically, crane service companies run into one of those lift projects where everything is seemingly stacked against them. Tight spaces filled with obstacles leave little room for crane assembly, let alone leaving little room to maneuver the load. Objects buried underground can limit the weight bearing load during the lift. And the weight, size and shape of the object to be lifted makes it necessary to expertly select the right crane — compact enough to work in the congested site yet still provide capacity — to pull off the challenging pick.

Crane service and rental company, Sterett Crane & Rigging of Owensboro, KY, recently completed work on one such impossible project for the City of Evansville, IN. Working with Bowen Engineering, a heavy civil construction company based out of Indianapolis, Sterett’s expertise was required to complete lid removal and replacement of the eight anaerobic digester tanks, critical to the water treatment program at the East and West Evansville Wastewater Treatment Plants (WWTP). 

“Having sufficient space alone to bring in and assemble the crane was challenging enough,” recalls Matt Crisp, Crawler Crane Fleet Manager for Sterett, about the congested project site at the 34-year-old facilities. “In order to remove the massive tank lids that weighed in excess of 250,000 pounds each, we needed to mobilize a crane that was small enough to fit into and maneuver in the tight area, while at the same time offer the capacity to lift the heavy lids.”

Out of the dozens of crane options from Sterett’s fleet, the one crane that stood out as the best, most efficient option for delivering success at the WWTP project was the Terex CC 2400-1 lattice boom crawler crane. With its 440-ton capacity, the Terex crane offered power to lift the heavy loads, and its Vario-Superlift structure feature proved to be the X-factor Sterett needed to successfully maneuver about the site at full load, according to the crane’s rated capacities.

Variable radius — the clincher

The digester tank lids were being removed and relocated for sandblasting and refurbishment. Each tank lid weighed between 258,000 to 274,000 pounds. The weight of the load required the CC 2400-1 crane to be equipped in its Superlift configuration, but as the crane’s body swung the lids into position to lower them onto the concrete cribbing, the Superlift tray had to maneuver past site barriers.

“The lids alone were 75 feet in diameter, and we had to rig to them at 16 points,” comments Crisp. “The plan was to pick the lid at a 91-foot radius, boom up, move the crane a short distance and then swing the ring into position for lowering it onto the cribbing. However, often a tank obstructed the path of the tray as we swung the load, and, at times, we had to be cognizant of the crane’s ground contact pressure.” 

Normally, assist equipment would be called in to unstack and restack tray counterweight as it maneuvers around the obstruction, but the CC 2400-1 crawler crane features variable tray positioning for the Superlift structure that increases the crane’s flexibility for use in congested areas. “The Vario-Superlift configuration on the CC 2400-1 crane offers a variable radius from 36 to 49.2 feet during operation,” explains Daiane Laidler, Regional Business Manager for Terex Cranes. “The Superlift can be configured with up to a 98.4-foot mast and counterweight tray with a maximum weight of 529,200 pounds.”

The ability to vary Superlift tray radius not only improved lift efficiency for Sterett, it also resulted in savings. “We saved money on matting, since we varied tray radius during the lift and were not required to stack and unstack the counterweight,” adds Crisp. “The (Vario) tray helped us to save time and money on the assist equipment as well.”

Precision and planning

Sterett mobilized its Terex CC 2400-1 crawler crane a short distance from Elberfeld, IN, to Evansville. Within two days, the 25 truckloads of crane, boom, counterweight and supporting equipment arrived at the Evansville WWTP. “There was only one way in and out of the plant site, and we had to maneuver around many underground lines and tunnels,” says Crisp.

Sterett’s five-man crew, along with an operator from Bowen running the set-up assist crane, quickly assembled the 440-ton crane complete with Superlift attachment, and it was ready for operation within three days of arriving on site. “It was a very tight and congested assembly area,” he adds.

For lifting the massive lids, the CC 2400-1 was configured with 137 feet of main boom. Crew members added 264,500 pounds of counterweight to the superstructure and additional 44,000 pounds of central ballast. The crane was equipped with the full 98.4 feet of Superlift mast, and the tray was loaded with 352,700 pounds of counterweight.

Rigged and ready for the lifts, the CC 2400-1 operated atop timber planks to help spread the ground contact pressure of the crane load. The initial pick of the 10-foot tall by 75-foot diameter lids was made at the 91-foot main boom radius, and the lid was lifted to a height of approximately 20 feet. “At the beginning of the lift, the CC2400-1 crane’s Superlift tray was positioned at its maximum 49.2-foot radius,” mentions Laidler.

Initially, the load was picked over the toes of the crawlers, and it was walked forward approximately 15 fee). The crane then rotated the lid to position it over concrete blocks that served as the platform for refurbishment. “As we swung the crane, we transitioned the Superlift tray’s radius from 49.2 feet to 36 feet to pass by the tank at the rear of the crane,” explains Crisp. “After passing the obstruction, we extended the counterweight tray back to a 49.2-foot radius to set the lid on the blocks. All this was done while under load without removing any counterweight.”

Crisp also recalls one particularly challenging lid lift, where the tank was nearby an underground tunnel, making the area sensitive to ground pressures. “The crane was positioned about 20 feet from the tunnel, but the tray was sitting next to the tunnel once we swung the load to its final resting place,” he says. Extra bracing was added to the tunnel to keep the ground contact pressure within the permissible limits.

Fortunately, the Terex CC 2400-1 crawler crane comes standard with the IC-1 control system that can calculate the distribution of the ground pressure along both track carriers and gives an estimation of the acting ground pressure. “It was definitely a learning experience with how much weight was gained or lost by shifting the weight in and out at radius,” mentions Crisp.

With an experienced crew of five Sterett members and five laborers from Bowen, the Evansville WWTP digester tank refurbishment project went off as planned, on schedule and within budget, despite the many challenges along the way. “Using the Vario-Superlift tray was the only way to do the first half of the job,” says Crisp. “The CC 2400-1 crane gave us the competitive edge we needed to get the job and the flexibility to complete the job as planned.”

Companies in this article
Latest