Spalled Concrete Joint Repair: Prep & Installation

Insight into the preperation of a spalled concrete joint and installation of the repair material.

Concrete contractors widened a structural joint for repair.
Concrete contractors widened a structural joint for repair.
Metzger/McGuire

The spalled concrete joint repair preparation and installation process when using semi-rigid or sand-modified semi-rigid repair materials is not unlike the initial joint filling process. It’s important to create clean, vertical edges at the outside of the joint repair to allow the repair material to bond to the joint walls and to clean the joint to the nominal depth of the original sawcut so the repair material has a structural base of support. 

This is part of a three-part series on spalled concrete joint repair. I cover repair material type selection in Part 2 and the causes of concrete joint deterioration in Part 1. 

Proper preparation of a joint to be filled requires that the joint sidewalls be mechanically cleaned using a diamond concrete blade on a walk behind concrete saw equipped with a HEPA dust collection system. The joint preparation process should remove all dirt, debris, saw cut laitance, etc. and through mechanically abrading the joint walls should remove any curing compounds or densifiers that flowed into the joint. A clean or “white” concrete along the joint walls is critical for proper joint filler adhesion.

A concrete joint widened for structural repair.A concrete joint widened for structural repair. Metzger/McGuire

Inherently weakened or “raveled” joint edges from improper saw cutting timing or defective saw blades lead to compromised joint edge integrity and a greater likelihood of joint edge deterioration if not addressed before joint filling. This issue has become more common recently as Type 1L and other carbon-friendly cement replacements have been rolled out to the concrete industry. 

Application of a semi-rigid aggregate to a concrete joint for repair.Application of a semi-rigid aggregate to a concrete joint for repair. Metzger/McGuireConcrete mixes using these replacements are generally less predictable in their set and finishing times vs. traditional Type I/II mixes and have led to challenges in the contractor’s ability to determine the optimal time to saw cut joints into a fresh slab. To restore joint edge integrity, it is often necessary to widen the joint to encapsulate the compromised edge and restore a clean/structurally sound edge to the joint.

These newly formed joint walls do not have to run to the full depth of the joint, but most repair material manufacturers call for a depth of 1/2 - 3/4 in. to allow for the filler to have sufficient sidewall contact to bond to and to more effectively key in the repair material. 

The result of this joint preparation will be an elongated “T” shape in which to place the filler.  As with new joint filler installation, the filler is slightly overfilled and the overfill razored or ground off to leave a seamless, flush profile across the floor.  When using semi-rigid joint fillers — modified or not — there is no need to re-sawcut the repair to re-honor the existing joint, as semi-rigid materials will not restrain slab panels and will still separate or tear if excessive joint opening occurs.

Majorjtrepsr2Metzger/McGuire

In joint repairs with existing semi-rigid joint filler installed — such as a joint exhibiting substantial joint filler separation or a joint where the filler profile was low and exposed joint edges — it is sometimes possible to cut or “mill” out the top 1/2 in. of the filler and use some of the initial filler as a base for the semi-rigid repair material. This is only possible where the initial filler was installed to the proper depth, remains intact and well bonded to the joint base, and is sufficiently rigid and comparable in hardness to repair material. 

Minor Joint RepairMetzger/McGuireUnfortunately, this is often not the case, and initial filler removal should be anticipated. There are several specialized saw blades on the market designed for filler removal. As a rule, polyurea joint fillers will be more difficult to remove and the process will be slower than removing epoxy fillers.

Majorjtrepsr1Metzger/McGuireStructurally re-building or re-nosing a wider deteriorated joint is more involved than repair using a semi-rigid filler. In this repair it is still critical to establish sharp, clean joint edges of 1/2 – 3/4 in. behind the spalled areas, but it is also important that the shelf of our new “T” joint be relatively uniform in depth, clean, and that the structural repair material used does not penetrate the existing joint base. 

Majorjtreprig4Metzger/McGuire

If the structural repair material flows into the contraction or construction joint, it can restrain the movement of the two slab panels and can lead to tearing or cracking of the panels if movement occurs. The best way to avoid this is to fill the existing joint with sand up to the level of the newly formed shelf. 

Majorjtreprig6Metzger/McGuireThe structural repair mortar is then placed into the channel, troweled slightly high, allowed to cure and then ground off flush with the floor surface. Failing to re-honor the existing joint at this stage is the biggest mistake contractors make and the most likely cause of repair failure. It is important to snap a chalk line across the repair (consistent with the joint line on both sides of the repair) and to re-sawcut a new joint completely through the repair mortar to the depth of the original sawn joint (or 2-in. minimum in deeper joints). 

Majorjtrepsr3

Once this new joint is cut, fill it with a semi-rigid filler to protect the repair material joint edges and ensure the slabs are not restrained.

It's important to recognize that when it comes to any building facility, the concrete floor is the literal worksurface for the entire operation. The longer maintenance or repair is deferred, the more complex and costly the repairs become.  

As long as floors have joints, the proper treatment and maintenance of those joints will continue to be critical in ensuring the long-term serviceability and durability of the facility, its operational productivity, and its safe operation.

This was part 3 of a three-part series on spalled concrete joint repair. Check out part 1, "Understanding Spalled Concrete Joints" and Part 2, "Spalled Concrete Joints Repair: Material Selection."

Page 1 of 32
Next Page