The Fundamentals of Generator Selection

A look at the basics of selecting mobile generators for your jobsites.

Many generators offer the ability to switch between 50- and 60-Hz frequencies to accommodate different equipment.
Many generators offer the ability to switch between 50- and 60-Hz frequencies to accommodate different equipment.

There are a number of things to consider when selecting a mobile generator for your application. The jobsite, required capacity and generator features are among those items to consider in order to make an informed and profitable decision.

“In most cases, rental centers and equipment dealers can provide excellent guidance for customers looking to rent or buy a generator,” states Brian Northway, product manager, Allmand Bros. Inc. “Their suggestions, however, are only as useful as the information they’re provided. Only with a comprehensive understanding of the equipment a customer will be powering, along with any other job-specific factors, can they determine the ideal generator.”

Clayton Costello, operations manager at CK Power, agrees, noting, “Because jobsite applications vary so widely, mobile generator selection should be taken on a case-by-case basis. A small commercial remodel, for example, will require a much different mobile generator than a big bridge refurbishment or road construction job.”

While some jobs may require a unit capable of handling significant surge loads, others may call for the ability to switch frequency or run on an external fuel supply. “The most important factor to consider — and the most common mistake that individuals make — is selecting a unit that doesn’t match the power required for the job,” Northway cautions.

“That’s why it’s so important to work closely with your supplier in order to select the mobile generator that best fits your jobsite’s particular requirements,” Costello emphasizes. “If needed, some suppliers can even customize a genset with the necessary load requirements, safety precautions and innovative features you need to be successful day in and day out.”

Read next: What to Consider When Selecting a Generator

Size It to demand

When it comes to generators, it’s important to pay careful attention to sizing. “An under-sized generator, or one too small to handle the load, will place strain on the unit and cause a shutdown or, at worst, damage to the unit,” says Todd Howe, global generator products manager, Doosan Portable Power. “A generator that is too large for the load will eventually result in ‘wet stacking,’ or a carbon buildup in the engine, causing a power loss.”

According to Costello, a generator should have a rated and maximum output just high enough to support the application. Rated output is the number of watts the machine can produce for an indefinite period of time, while maximum output is typically viewed as the highest number of watts the generator can produce for brief periods.

To determine power requirements, list the combined wattage of all the equipment you will be loading onto the genset by both the power required to start the equipment and the power needed to run it. The sum total of the running power is the generator’s required rated output. The sum total for starting power is the maximum output required.

“Take those numbers and add a 10% buffer as a safety precaution,” Costello advises. “If you choose a genset that doesn’t meet the demands of its application, the generator will fail to power your site adequately and wear out faster.”

Read next: Generators: Motor Starting Sizing Questions

However, it’s important not to build too large a buffer, since having more power than needed can be detrimental. “Ideally, a generator should have enough power to run everything at a site, but not so much that it will be running significantly below its rated load capacity,” Northway states. Diesel generators operated below 50% to 60% capacity are at risk of wet stacking.

To minimize this risk, some contractors may opt to run two smaller generators in parallel. Paralleling is when two or more generators are electrically coupled together using special equipment to form a larger capacity power source. If the two generators are the same size, it effectively doubles the power output.

“The basic premise behind paralleling is to take two generators and connect them together in such a way that they combine their output to make a theoretically bigger generator,” says Howe.

“This provides workers the option of shutting down one unit to adjust for demand,” Northway points out. “Although this may increase initial costs, it can deliver savings for some jobs by reducing downtime and improving application flexibility.”

Adjustable output

Although a generator’s primary purpose is to deliver electricity, multiple output settings can increase its versatility.

“Units equipped with a frequency switch are beneficial if the generator will be used with both 50- and 60-Hz equipment,” notes Northway. “Many generators can switch between both frequencies to accommodate different equipment. Similarly, generators that offer multiple voltage settings, as well as the ability to switch between single- and three-phase electric power, provide owners and operators with improved versatility.”

An automatic voltage regulator (AVR) can further expand the generator’s flexibility. “A surge of power is required as equipment starts and then the power need tapers off as equipment runs normally. An AVR helps ensure the output voltage remains consistent, even under varying loads as you start and turn off your equipment throughout the workday,” Costello indicates.

If the generator will frequently be used to start large motors with variable loads, Northway also recommends a model with a heavy-duty, oversized alternator. This will ensure sufficient power to start large motors without surging.

Read next: Don't Let Generator Sizing Trip You Up

Fuel capacity

Runtime refers to the amount of time a generator can run before refueling. “In general, you’ll want to choose a generator that meets your jobsite’s load requirements at 100% throughout a typical workday,” Costello advises. “Anything beyond that is extra. Anything less, and you’re losing precious work time while your crew stands around [waiting] for the generator to be refueled.”

For situations where more time between fuel fills is needed, generators are available equipped with large fuel tanks and offering runtimes exceeding 24 hours. There are also generators capable of switching from the onboard fuel source to an external one.

“Drawing from an external source can drastically extend runtime compared to units that are limited to an onboard fuel supply,” Northway comments. “While this option is available from many manufacturers, some have made it standard, while others do not offer it at all.”

Another option worth consideration is an automatic fuel priming system. “This system allows the operator to simply turn the key back to start and the system will prime itself,” Northway points out. “Although no one plans to run a generator completely out of fuel, it does happen, and having a self-priming generator can cut downtime significantly.”

Latest in Towable Generators
Page 1 of 19
Next Page

Create a free For Construction Pros account to continue reading