The U.S. Army Corps of Engineers awarded Kiewit-Turner a $571 million contract to finish construction on the over budget and behind schedule U.S. Department of Veterans Affairs hospital in Aurora, Colo. The project's completion date has also been pushed back from 2017 to January 23, 2018.
Kiewit-Turner served as the original general contractor on the project since 2010 but in 2014 won a judgment against the VA and walked away from the project after a Civilian Board of Contract Appeals decided the VA had breached its contract with Kiewit-Turner.