How Cranes Are Helping Extend a Dam's Height by 65 Feet

Three Linden Comansa tower cranes are helping place over 85,000 cu. yd. of concrete to extend the Cambambe hydroelectric power station dam in Angola

Heightening the Cambambe hydroelectric power station will increase the capacity of the reservoir from 0.77 to 2.12 square miles, and allow the four existing generators to produce 65 megawatts each instead of the present 45.
Heightening the Cambambe hydroelectric power station will increase the capacity of the reservoir from 0.77 to 2.12 square miles, and allow the four existing generators to produce 65 megawatts each instead of the present 45.

The challenge:

Raising the Cambambe hydroelectric power station dam in Angola by 20 meters

The players:

Norberto Odebrecht

The process:

In December 2015 the regrowth works of the Cambambe hydroelectric power station, in the Kwanza River, about 180 kilometres southeast of Luanda, the capital of Angola, will be concluded. This dam currently supplies power to seven cities and approximately 8 million people.

Built in 1962, the station is being renovated and expanded since 2009 to increase its energy production by 80 percent. In 2014, Cambambe was certified with ISO 9001, 14001 and 18001 seals, being the first hydroelectric project in Africa to obtain such recognition.

Part of the project which is being conducted by the Brazilian construction company Norberto Odebrecht is the rise of the dam’s height by 65 feet. This heightening will increase the capacity of the reservoir from 0.77 to 2.12 square miles, and allow the four existing generators to produce 65 megawatts each instead of the present 45.

In order to put into place the over 85,017 cubic yards of concrete needed to rise the dam, Odebrecht is using three Linden Comansa tower cranes: two 21LC750 with maximum load capacity of 105,821 pounds and a 21LC400 with maximum capacity of 39,683 pounds.

The first 21LC750 was located on the left bank of the Kwanza River, erected with fixing angles on a special concrete foundation which, given its short width, was anchored to a rock on the river bank. It was mounted with a freestanding height of 258 feet, the maximum possible height with 8-foot-wide mast sections (fourteen D36 sections), and a jib length of 262 feet.

On the right bank, a second 21LC750 was erected with a freestanding height of 286 feet, achieved with 12 sections D36 — as her "sister" in the left margin — increased by three 16-foot-wide D56 sections at its bottom. Another concrete foundation was anchored on the riverside to allow this crane’s assembly on fixing angles.

After a year and a half working in concreting and materials lifting tasks, the first 21LC750 (left bank) was relocated within the jobsite and substituted by a 21LC400, which was erected with a freestanding height of 262 feet and a jib length of 229 feet. This crane was assembled on the same fixing angles of the previous 21LC750, so it was necessary to have two transition sections in order to allow the progression from the 13-foot-wide fixing angles to the 8-foot-wide D33 mast section.

The relocated 21LC750 is currently working on the construction of the power house (or power generation centre) where it was assigned to moving precast segments up to 41,887 pounds of weight for the new water tunnels, as well as lifting and placing all the electromechanical gear that will allow the production of energy, such as turbines and generator sets.

The assembly and jacking-up of the first 21LC750 was performed by Linden Comansa’s technical assistance service team, while the remaining assemblies, jacking-ups and technical service was entrusted to IBERGRU, the official distributor of Linden Comansa in Portugal since 2002.

 

Page 1 of 80
Next Page