Four Cranes Work in Unison on Crucial Lifts for WI Highway Project

A fleet of Manitowoc 2250 crawled cranes helped assemble several new overpass bridges as well as expand traffic lanes and reconstruction several interchanges and roundabouts

A quartet of Manitowoc 2250 crawler cranes took center stage in the assembly of several new overpass bridges as part of a $61 million highway project in Wisconsin. The work also included the expansion of highway US 41 traffic lanes, the reconstruction of several of its interchanges and the addition of 40 roundabouts.
A quartet of Manitowoc 2250 crawler cranes took center stage in the assembly of several new overpass bridges as part of a $61 million highway project in Wisconsin. The work also included the expansion of highway US 41 traffic lanes, the reconstruction of several of its interchanges and the addition of 40 roundabouts.

The challenge:

Assemble new overpass bridges, expand traffic lanes and reconstruction several interchanges and roundabouts as part of a $61 million Wisconsin highway project

The players:

Dawes Rigging & Crane Rental

The process:

A quartet of Manitowoc 2250 crawler cranes took center stage in the assembly of several new overpass bridges as part of a $61 million highway project in Wisconsin. The work also included the expansion of highway US 41 traffic lanes, the reconstruction of several of its interchanges and the addition of 40 roundabouts.

Dawes Rigging & Crane Rental, Milwaukee, Wis., handled the lifting work, choosing the fleet of Manitowoc 2250 crawler cranes for their reach and capacities. Scott Jerome, senior branch manager at Dawes, said the lifts, some of which required all four cranes to work in unison, required cranes that could lift heavy loads with precision.

“The 300-ton capacity cranes were just what we needed for the large pick weights associated with many of the lifts, especially the prefabricated tub girder structures that weighed up to 120 tons,” he said. 

The cranes’ 330-foot main booms were crucial to the lifts, raising loads above and across several traffic lanes and other road construction equipment to carefully position them on concrete support piers. The 2250s also endured shifting seasons to complete the project, ranging from heavy snow in February to sweltering heat in July.

Companies in this article
Latest