LAX Central Utility Plant Project Tops Out

Construction workers placed the final structural steel beam atop the plant, which is designed with strict seismic criteria to help protect the facility and airport utilities during an earthquake.

A rendering of the $438 million (development cost) design-build replacement Central Utility Plant project at Los Angeles International Airport, which is being built by Clark/McCarthy, A Joint Venture.
A rendering of the $438 million (development cost) design-build replacement Central Utility Plant project at Los Angeles International Airport, which is being built by Clark/McCarthy, A Joint Venture.

The new Central Utility Plant (CUP) at Los Angeles International Airport (LAX) reached a major construction milestone when construction workers placed the final structural steel beam atop the building’s frame on January 24, 2012. Currently on schedule for construction completion in summer 2014, the $438 million (development cost) design-build project is being built by Clark/McCarthy, A Joint Venture.

In just four weeks, construction workers from Schuff Steel used a Manitowoc 999 Lattice-boom crawler crane with a reach of 140 feet to erect 1,400 tons of structural steel, creating the frame for the new CUP. An audience of approximately 300 project stakeholders and construction workers celebrated the ‘topping out’ during a ceremony held near the construction site.

As a part of the event, attendees signed the final I-beam adorned with an American flag and an evergreen tree. The beam was then lifted 75 feet high and attached to the top of the structure.  The tradition of attaching a tree and flag to the final structural beam has been practiced by construction workers for over 1,000 years.  The tree represents growth, life and good luck for the construction workers and the building’s future occupants. The flag is displayed as a patriotic symbol that signifies the united effort by the project team to achieve a common goal.

“An interesting aspect pertaining to the CUP structure is that it was designed as an essential facility with stringent seismic drift criteria to protect the facility during a major earthquake,” said Kevin Carpenter, design manager for Clark/McCarthy. “Furthermore, some of the cogeneration equipment that will be installed on upper floors, including the two Combustion Turbine Generators that weigh in excess of 60 tons each, requires the steel frame to be extremely stout.”

The 70,000-square-foot facility has a steel frame that weighs in excess of 1,400 tons, or 40 pounds per square foot—about 30% higher than an OSHPD hospital in California.

Out with the old, in with the new

The new CUP is being built to replace the existing 50-year old facility with a modern, state-of-the-art, computer managed utility plant providing enhanced passenger comfort and reliability of utility service and safety within the newly renovated modernized terminals at LAX. The existing CUP will service the airport throughout construction. Upon project completion, the replacement will be brought on-line and the old CUP will be decommissioned and demolished.

Serving as general contractor for the project, Clark/McCarthy’s contract includes demolition of the existing 50-year-old CUP as well as construction of a new 64,000-square-foot, steel-framed replacement CUP with a 20,000-ton cooling capacity. The project also entails the installation of  associated equipment, such as a stand-by boiler, primary and secondary chilled water pumps, cooling towers, electrical systems and switchgear.

A new maintenance shop and offices and an above-grade thermal energy storage (TES) tank with capacity for 1.6 million gallons of water and 15,500 ton-hours of cooling is also being built.  Other work includes:

  • replacement of approximately 18 miles of pipe and duct bank that service the entire Central Terminal Area (CTA) with utility distribution, electrical and communications systems as well as reclaimed water, fire water and potable water systems;
  • installation of several miles of new distribution piping throughout the CTA and beneath existing main entrance roadways throughout the airport;
  • and an upgrade of pump rooms and air handling equipment in 21 different locations within all terminals, administrative buildings and the LAX Theme Building.

Systems and their components for the new CUP were designed and constructed to achieve LEEDSilver certification from the U.S. Green Building Council.

Clark/McCarthy, A Joint Venture is a joint venture between Clark Construction Group and McCarthy Building Companies. Additional project partners include: Gruen Associates, Los Angeles, architect; Arup, Los Angeles, mechanical, electrical, plumbing, structural, and commissioning engineer; Capital Engineering Consultants, Rancho Cordova, Calif., mechanical consultant; Greenform, Los Angeles, sustainability consultant; and PID Engineering, San Diego, cogeneration consultant.

For more information about the project and project team, visit: http://www.clarkmccarthylaxcup.com/

Latest in Lifting Equipment
Durability That Gets The Job Done.
Sponsored Content
Page 1 of 236
Next Page