Demolition In Dense Metro Area Comes Off On Time, On Budget

Rachel Contracting takes down a former General Mills R&D facility in Minneapolis, Minnesota

The concrete was crushed on-site for beneficial reuse. The team was also able to recycle ferrous and nonferrous metal, and any debris went to the landfill.
The concrete was crushed on-site for beneficial reuse. The team was also able to recycle ferrous and nonferrous metal, and any debris went to the landfill.
National Demolition Assoc.

In 2019, breakfast cereal giant General Mills said “Cheerio” to its former research and development building in Minneapolis, Minnesota. NDA member Rachel Contracting was asked to bid this private project by a local general contractor it had worked with successfully in the past, which was planning on redeveloping the property into multi-family housing.  

Project Statistics

  • Job duration: 7.5 months
  • Floor space: 384,000 square feet
  • Crew size: 6-10 workers
  • Concrete crushed and recycled: 30,000 tons
  • Ferrous and nonferrous metal recycled: 1,000 tons
  • Total amount recycled: 85%

“Given our history with the general contractor, there was certainly a relationship to leverage, but our value-added experience from both our estimating/project management personnel and our field expertise played a part,” says Phil Baumer, Rachel Contracting’s director of business development. “Ultimately, our price point was competitive enough that the general contractor decided to retain Rachel Contracting for the demolition.”

Rachel Contracting cleared a total of 384,000 square feet of floor space.Rachel Contracting cleared a total of 384,000 square feet of floor space.National Demolition Assoc.The Rachel team mobilized on April 1, 2019, and completed the project seven and a half months later on Nov. 15, 2019.

The structure was comprised of six buildings that made up the research and development building. “The original building had been added onto over the years, so there was a likelihood of various hazardous materials present,” Baumer says.

Some of the buildings were as high as six stories, with a total of 384,000 square feet of floor space. Additionally, there were five hydraulic elevators that required abandonment. Rachel Contracting had a plan in place to recycle and reuse as much concrete and scrap as possible.

The interior was stripped to clean out the building, salvaging mechanical equipment, furniture, and fixtures that General Mills left behind.

“The interior GWB walls, AT drop ceilings and carpet were also selectively removed to get clean concrete floors,” Baumer says.

After the building was completely gutted, Rachel Contracting used a high-reach excavator to begin concrete recycling in a top-down process. The concrete was crushed on-site for beneficial reuse. The team was also able to recycle ferrous and nonferrous metal, and any debris went to the landfill.

“Our crews ranged from six to 10 operators and laborers,” Baumer says. “At the peak of the project schedule, there were 10 Rachel team members, and our lowest crew were six and fluctuated in the interim.”

Equipment Used

  • 1 Liebherr 954 C
  • 1 CAT 349 excavator
  • 4 CAT 336 excavators
  • 4 CAT and Bobcat skid steers
  • 2 rubber tire loaders
  • 1 CAT 966
  • Genesis GDR 300 attachment
  • DemoPro GDP 900 attachment
  • NPK hydraulic hammer attachment

Although it seems like a pretty straightforward job, as with any demolition project, there were some challenges. “The property was surrounded by single-family homes and multi-family units. Dust control was a major component due to the density of residences and people. Working in a major metropolitan area was certainly Over 85% of the materials generated on the project were recycled.Over 85% of the materials generated on the project were recycled.National Demolition Assoc.a challenge, too, with pedestrian traffic, vehicle traffic, etc. Debris segregation for beneficial reuse was another challenge with various materials being processed. Due to the age of the buildings, there was unidentifiable asbestos found; there was not a full survey done.”

Rachel Contracting, as well as the general contractor, consider the demolition a success. The project was delivered on time and on budget, and recycled goals were met, too. Over 85% of the materials generated on the project were recycled. More than 30,000 tons of concrete were crushed and recycled. Over 1,000 tons of ferrous and nonferrous metal were recycled.

Latest